(804) 234-8623

Grease Interceptor Rules in Chesterfield County: The 80% Rule, Every-Two-Weeks, Three Years

Midlothian, Chester, Bon Air, Chesterfield Courthouse. Chesterfield is the one jurisdiction in the metro with an explicit fill line, a self-inspection clock and a record-retention period written into code. Sec. 18-103, quoted.

Call (804) 234-8623

Who must have one

“All industrial users that generate oil and grease of animal or vegetable origin shall install adequately sized grease interceptors or other grease removing pretreatment equipment as required by the director. Grease interceptors shall be installed at the user’s expense, when such user operates a cooking establishment.” (§18-103(a)(1))

Devices must be “of a type, design, and capacity approved by the Department of Building Inspection of Chesterfield County” and “readily and easily accessible for user cleaning and county inspection” ((b)(1)). Sizing follows the International Plumbing Code and “shall also consider the type of food being prepared, seating capacity, frequency of maintenance, equipments connected to the trap” ((b)(2)(a)). If the menu or seating changes, you must evaluate the size and notify Building Inspection in writing within two weeks ((b)(2)(j)). Garbage disposals and non-grease sources may not connect to it ((b)(2)(i)).

The three numbers

DutySectionText
Self-inspect18-103(b)(2)(b)“Inspect the grease interceptor, oil/water separator or similar device every two weeks if not sooner.”
Pump18-103(b)(2)(e)“shall be pumped out and cleaned, at a minimum, when 80 percent of the retention capacity is filled with oil and grease and/or solids, or on a more frequent basis as determined by the industrial user or the county.”
Keep records18-103(c)(1)“The industrial user shall maintain a written record of trap, oil/water separator, interceptor or similar device maintenance for three years. All such records shall be available for inspection by Chesterfield County at all times.”

Read the 80% rule carefully

It is a ceiling, not a target. The same section requires you to operate the device “in a manner to consistently achieve attainment of oil and grease limit” — meaning any sample downstream must meet §18-93(b): 300 mg/L for flows under 25,000 gallons a day, 200 mg/L from 25,000 to 50,000, 100 mg/L above that ((b)(2)(h)). An interceptor at 80% is not separating; it is passing grease. The city of Richmond’s program and the industry plan at 25%. We plan Chesterfield kitchens at 25% too, and log the two-week readings the code requires so the file shows you never approached 80.

Also required on site

If grease from your kitchen blocks the sewer

“If at any time Chesterfield County’s sewerage system is obstructed that causes a sewer overflow ... and an overflow or failure of the sanitary sewer collection system to convey sewage can be attributed in part or in whole to accumulation of grease in Chesterfield County’s sewer main(s), Chesterfield County will take appropriate enforcement actions ... Industrial user’s shall reimburse the county for all the cost associated with cleaning the sewer system. The industrial user will also be liable for all the damages to the environment, property and personnel.” (§18-103(d)(1))

A kitchen without a device, or with an undersized one, goes on “a compliance schedule not to exceed six months” ((d)(3)). All pretreatment is “at the industrial user’s expense” (§18-97).

Contacts and disposal

Chesterfield Utilities 804-748-1271, utilities@chesterfield.gov; water and wastewater emergencies 804-748-1310. Hauled grease-trap waste is accepted at the Proctors Creek plant in Chester with a detailed manifest per load.

What we do in Chesterfield

Full pump-outs; a receipt written to §18-103(c)(1) with date, gallons, percent-full before service and the hauler; a two-week inspection log sheet for your wall; and, for a new or changed kitchen, the sizing worksheet Building Inspection will want.

Chesterfield kitchen?

Call with the unit size. Three-year file, two-week log, 25% plan.

Call (804) 234-8623
Plain-English guidance, not legal advice. County quotations are from each county’s Code of Ordinances as published on Municode (Henrico version dated Sep 12, 2026; Chesterfield and Hanover read the same day), read 2026-10-08; state quotations are from the 2021 Virginia Plumbing Code on ICC Digital Codes and from law.lis.virginia.gov. Confirm current text with the county utility named on the page.
📞 (804) 234-8623